Figure 2-69. Replacement Pendulum Line Construction Details.
e. Pass tapered cord end through deployment bag pendulum line attaching loop and attach tapered end to splicing
aid.
f. Pull splicing aid back into cord casing at 6 1/2-inch mark and work aid back through cord casing to outside at 8-
inch mark (figure 2-70).
g. Remove tapered cord end from splicing aid. Sear tapered end and make an overhand knot in cord running end at
a point 1 inch back from seared tapered end. Stretch cord loop to draw knot against cord casing.
2-123