2-16. Packing the 22-Foot Cargo Extraction Parachute (cont).
Figure 2-28. Suspension Line Stowage Flap Rolled into Open End of Deployment Bag.
(4)
Fold extended adapter web from left to right across rolled suspension line stowage flap (figure 2-29).
(5)
Using a single length of 1/4-inch cotton webbing, make left bag closing tie by passing one end of thread
through left bottom bag closing loop from right to left, up behind adapter web, through top bag closing loop
from left to right, secure ends together over adapter web, with a surgeon's knot and a locking knot. Trim tie
ends to 2-inches (figure 2-29).
(6)
Using a single length of 1/4-inch cotton webbing, make right bag closing tie by passing one end of thread
through right bottom bag closing loop from left to right, up behind extraction line or adapter web, as
applicable, up through right side bag grommet, through right bag closing loop from right to left, secure ends
together over adapter web, with a surgeon's knot and a locking knot (figure 2-29).
2-46