2. Confirming proper layout. Perform a four-line check to confirm that the suspension lines are in proper
layout and a three-line check to confirm that the suspension risers are in proper layout. Proceed as
follows:
a. One packer will take a position between the separated suspension lines near the skirt of the canopy,
facing the suspension risers.
b. Place lines 1 and 60 in the right hand and lines 61 and 120 in the left hand. Hold these suspension
lines in a manner that will keep the lines separated and identifiable in each hand.
c. Walking slowly, trace the four lines to the connector link assemblies. Line 1 should be at the top of
the first connector link on the left (rigger view), line 60 should be at the bottom of the sixth connector
link, line 61 should be at the top of the seventh connector link and line 120 should be on the bottom of
the twelfth connector link.