2-17. Packing the 64-Foot Cargo Parachute, Model G-12E (cont).
4839-083
Figure 2-87. Forming the Second Line Stow.
(o) Stow the risers and remaining lines to a point 18 inches from the clevis (figure 2-88). An S-
fold is not
made in the last stow.
(p) Trim all the webbing ends to 2 inches.
(11) Closing the deployment bag. Closing the deployment bag requires a rigger to be located on each
side of the bag to perform the following:
(a) Untie the two cluster attaching straps securing the suspension line stowage flap at the bottom
of the bag.
(b) Roll the stowage flap as tight as possible toward the bag open end (figure 2-89)
(c) Lay the closing flaps outside the bag.
(d) Insert the rolled stowage flap into the bag.
(e) Fold the closing flaps in the sequence shown in figure 2-90.
2-92