6. Hand tack each riser below the connector link with one turn double tape lacing and tying with an
overhand knot.
7. Remove parachute from hanging device and place in proper layout.
APPLICATION OF MARKINGS
Apply markings as follows:
NOTE
When a parachute component is placed in service, the month and
year of date placed in service shall be marked on it.
1. Canopy. On cell with data block.
2. Risers. On front of front riser.
3. Pilot chute. Anywhere on fabric area that will be visible after marking.
4. Slider. Anywhere on fabric area that will be visible after marking.
5. Risers. Stencil riser on fabric, in suitable location (near data tag).
6. Allow markings to dry 20 to 30-minutes.
Connector Link
Tacking