exceed the width of the applicable parachute pack or
deployment bag.
A.
Individual gore group rolling completed.
g. Continue rolling the canopy toward the lower
B.
Rolling the canopy.
end of the suspension lines and risers, if applicable,
C.
Suspension lines on rolled canopy.
locating the lines and riser webbing around the center of
D.
Rolled canopy assembly on parachute pack.
the roll (C).
h. As applicable, disconnect the suspension lines /
d. Release tension and disconnect the canopy vent
risers from the attaching device and place the rolled
from the vent attaching device.
canopy assembly on top of the pack / deployment bag
e. Fold the canopy vent down between the rolled
inside.
gore groups to a point within 18 inches of the canopy
i. Secure the rolled canopy assembly within the
skirt lower edge.
confines of the pack / development bag using either the
f. Beginning at the folded upper end of the
straps or webbing of the pack or a length of suitable type
canopy, roll the canopy tightly toward the canopy skirt
cord (D).
(B). Insure the width of the rolled canopy does not
2-25