TM 10-1670-268-20&P 0016 00
0016 00-5
e. Install four ½-inch X 3 7/32-inch side rail bolts, and ½-inch flat washers, on each side of the
platform into clevis bolt-holes 31 through 34 and corresponding holes in the fitting.
(1)
Install the two remaining side rail bolts (35 and 36), washers and bushings. Start the bolts
two or three turns by hand.
f.
Using a ¾-inch wrench or socket, tighten the side rails bolts to within one-quarter inch of the top
of the flat washer.
g. Working from the outside to the inside (side rail bolt 31 then 36), tighten the remaining side rail
bolts (31 through 36).
2. Install the weldment on each side of the aft end of the platform as follows:
a. Position weldment so the 2 bolt-holes at each end match up with bolt holes on the link.
b. Install ½-inch diameter x 4½-inch cap bolts; insert bolts from the outside of the link assembly.
Use a flat washer under bolt head and nut. Start the bolts two or three turns by hand.
WELDMENT
ASSEMBLY
LINK
ASSEMBLY