TM 10-1670-268-20&P 0016 00
UNIT MAINTENANCE
TYPE V AND DUAL ROW AIRDROP PLATFORM
OUTRIGGER ASSEMBLY
0016 00-1
THIS WORK PACKAGE COVERS:
Remove
Clean
Inspect
Replace
Install
INITIAL SETUP:
Tools:
Bar, Pry (Item 1, WP 0020 00)
Brush, Wire (Item 2, WP 0020 00)
File, Mill (Item 7/8, WP 0020 00)
Socket, ¾-IN. (Item 17, WP 0020 00)
Socket, 9/16-IN. (Item 19, WP 0020 00)
Wrench, Box and Open, ¾-IN. (Item 23, WP 0020 00)
Wrench, Box and Open, 9/16-IN. (Item 28, WP 0020 00)
Wrench, Impact (Item 30, WP 0020 00)
Materials/Parts:
Brush, Scrub (Item 1, WP 0036 00)
Dishwashing Compound (Item 3, WP 0036 00)
Locktite, Thread, Blue (Item 4, WP 0036 00)
Rag, Wiping (Item 5, WP 0036 00)
Tape, Adhesive, 2-IN. (Item 6, WP 0036 00)
Webbing, Tiedown, CGU-1B (Item 8, WP 0036 00)
Applicable Configurations:
All
Personnel Required:
Two/Three, 92R (10) Parachute Rigger
General Safety Instructions:
Observe all warnings and cautions.
REMOVE
1. Remove outrigger assembly as follows:
a. Place the platform on the dedicated assembly area so that the installation holes on the two
panels with outriggers installed are accessible from the bottom of the platform.
CAUTION
Outrigger mast assemblies cannot stand on their own. All
personnel must stand clear of the path of the fall of the mast
assemblies during disassembly of outrigger masts.
b. One person stands between the upright outrigger mast assemblies and holds them in place by
the handles. A second person releases the CGU-1B cargo tie down strap holding the mast
assemblies together.
c. While one-person holds one mast assembly upright, two people lower the other mast assembly
into the mast link cradle area on the link, retracting the knob handles. Two persons then lower
the second mast assembly into the second mast link.