2-16. Packing 12-Foot Cargo Parachute (cont).
(3) Working from right to left and moving bag toward tension plate, stow remaining suspension lines
securing each stow with a rubber retaining band, making last stow at a point 5 Inches from riser
connector loops (figure 2-31).
4706-035
Figure 2-31. Suspension Line Stow Complete.
n. Riser Securing Ties.
(1) Position riser connector loops at a point immediately below open end of bag.
(2) Cut two 18 inch lengths of 1/4 inch wide cotton webbing for use as tie material.
(3) Working in a counterclockwise direction, thread one 18 inch webbing length through the left bottom
bag tie loop, through the left riser connector loop and through the left top bag tie loop (figure 2-32).
4706-036
Figure 2-32. Riser Securing Ties.