4-16. ASPSU - Inspect
4-16
This task covers: Inspection
INITIAL SETUP
Personnel Required:
43E (10) Parachute rigger
Equipment Condition:
NOTE:
The instructions pertain to the functional group number sequence 02 in the MAC and RPSTL.
INSPECTION
1. Insure that the cutter mechanism has not been fired.
(You should not be able to see the blade.)
2. Insure that the four captive screws are tight.
3. Insure that the safety tag and pin assembly is
securely attached.
4. Inspect for dents, cracks, or foreign material.
END OF TASK