16. Rigger check number 5.
NOTE
There should be a minimum of 8 stows on each panel.
17. Remove the connector links from the tension plate.
18. Fold the excess slack from the remaining suspension lines over the stowed
suspension lines.
TYING CONNECTOR LINKS AND SUSPENSION LINE PROTECTIVE COVER
To secure the packed deployment bag, continue as follows:
1. Unroll suspension line protector cover and cover suspension lines.
NOTE
Ensure the risers are still in proper layout.
2. Using a 14-inch length of Type I, ¼-inch, cotton webbing, pass an end through the right bottom
connector link tie loop, through right pair connector links, through top right connector link tie loop, and
through cover tie loop.