ARMY TM 10-1670-281-23&P
AIR FORCE T.O. 13C5-32-2
NAVY NAVAIR 13-1-32
4839-154
Figure 2-153. Bridle Line Attachment Details.
(b) Replacement. Replace a damaged or missing tiedown loop on the static line pilot parachute
bag by fabricating as follows:
1 If applicable, remove the damaged loop by cutting the stitching which secures the loop to the
pilot parachute bag.
2 Cut a 5-inch length of 1-inch wide, type II cotton webbing and wax the ends.
3 Double the webbing length, aline the ends, and position the folded webbing on the bag in the
original tiedown loop location.
4 Form the 1 1/4-inch long loop and secure the webbing to the bag by stitching a 1 -inch long
single-X-box-stitch formation with one double end, according to the details in figure 2-154.
Stitching will be made with a light-duty machine using size E nylon thread, 7 to 11 stitches per
inch.
d. Replacement. Replace an unserviceable 15-foot long static line with a serviceable item from stock.
2-213