TM 10-1670-327-23&P
UNIT MAINTENANCE
MC-6 PERSONNEL PARACHUTE SYSTEM
NSN 1670-01-527-7537
MAIN PACK TRAY CLOSING PIN COVER
REPLACE
INITIAL SETUP:
Tools
Personnel Required
Sewing Machine, Medium Duty (Item 59, WP
92R (10) Parachute Rigger
Materials/Parts
Equipment Condition
Lay out on packing table or other suitable area.
REPLACE
1. Using a stitch removal tool, carefully remove the damaged pin protector flap.
2. Remove any loose stitching.
3. Center the new pin protector flap (figure 1, item 1) overlapping the binding tape at the end of the top
flap.
1
Figure 1. Replace Damaged Pin Protector Flap.
4. Using a medium duty sewing machine and size E nylon thread, 7 to 10 stitches per inch and 3/8 of an
inch wide, sew the pin protector flap to the binding tape.
END OF WORK PACKAGE
0046 00-1/(2 Blank)