TM 10-1670-265-12&P
T.O. 13C7-1-12
4-21. G-12E - SERVICE (Cont)
4-21
PACKING (Cont.)
8.
Tying the canopy, suspension lines, and center line (cont).
COMBINED SUSPENSION LINE GROUPS
h.
Beginning at a point 10 feet below the skirt reinforcement, tie both groups of suspension lines and the center
i.
Secure the tie with a surgeon's knot and a locking knot. Trim the tie ends to 2 inches.
j.
Repeat steps h and i above at subsequent 10foot intervals along the remaining length of the suspension
lines.
GO TO NEXT PAGE
Change 1 4-61