TM 10-1670-327-23&P
DIRECT SUPPORT MAINTENANCE
MC-6 PERSONNEL PARACHUTE SYSTEM
NSN 1670-01-527-7537
MAIN CANOPY SUSPENSION LINE ATTACHING LOOP
REPAIR, REPLACE
INITIAL SETUP:
Tools
Personnel Required
92R (10) Parachute Rigger
Sewing Machine, Double Needle (Item 54, WP
Sewing Machine, Medium Duty, Zig-Zag (Item
Sewing Machine, Light Duty (Item 56, WP 0097
Materials/Parts
Equipment Condition
Webbing, Nylon, Bally #8962 3/8-inch wide (Item
Unpacked
Pencil, China Marker, Yellow, (Item 35, WP 0109
NOTE
A double needle sewing machine may be substituted for a single needle sewing machine.
REPAIR
Repair Main Canopy Suspension Line Attaching Loop
1. Remove damaged suspension line attaching loop (figure 1, item 1) by cutting loop with a pair of
shears even with the anti-inversion net (figure 1, item 2). If previously repaired, carefully remove
stitching and remove damaged suspension line attaching loop.
2
1
Figure 1. Suspension Line Attaching Loop.
0092 00-1