TM 10-1670-268-20&P 0012 00
0012 00-4
4. Replace bushings (6) by sliding in either end of side rail (1) and aligning with a side rail bolt-hole.
NOTE
Ensure all side rail bushings are present representative of the
length of the platform IAW Table 1, WP 0012 05.
5. Install side rail bolts (2) and flat washers (3). Start each bolt two or three turns by hand.
6. For the dual row platform, install the link IAW WP 0004 00.
7. For the type V platform, install the tandem link assembly to include side rail bolts (2) and flat washers
(3) IAW WP 0004 00.
8. Fully tighten side rail bolts (2) and flat washers (3), working from the center toward each end of
platform.
9. Fully tighten side rail/outboard roller pad bolts (4) working from the center toward each end of
platform.
NOTE
Each suspension bracket assembly, when installed on the platform
replaces 3 side rail bushings.
4
5
6
1
3
2