TM 10-1670-327-23&P
0015 00
2
4
3
1
Figure 35. Pulling Remaining Slack of Control Line.
7. S-fold all the slack in the control line (figure 36, item 1) 2 to 3 inches then secure using the retaining
band (figure 36, item 2) attached to the guide ring (figure 36, item 3), ensure enough wraps of the
retaining band are used to firmly secure the s-fold. Repeat steps 4-7 for the left riser assembly and
control line.
3
1
2
Figure 36. S-folding Slack in Control Lines And Securing with Retaining Band.
LONG-FOLDING THE CANOPY
1. The anti-inversion net and lower lateral band of the canopy will be folded 180 degrees, with the right
group (figure 37, item 1) folded first.
2. Grasp the edges on the right side of the anti-inversion net (figure 37, item 2) with the left hand and
the lower lateral band in the right hand. Fold edges slightly over the air channel (figure 37, item 3)
(approximately 2 inches). Place the first packing weight (figure 37, item 4) on the lower lateral band.
0015 00-26