TM 10-1670-327-23&P
0015 00
CLOSING DEPLOYMENT BAG AND STOWING SUSPENSION LINES
1. Pull suspension lines (figure 45, item 1) over the top of the deployment bag (figure 45, item 2), fold
the side flaps (figure 45 item 3) of the deployment bag over the stowed canopy anti-inversion net
(figure 45 item 4).
4
1
3
2
Figure 45. Closing Deployment Bag and Stowing Suspension Lines.
2. Place the locking stow panel (figure 46, item 1) over the side flaps. Insert the locking loops and
connector links tie loops through the slots in the stow panel ( figure 46, item 2), Insert the stow hooks
(figure 46, item 3) in the locking loops (figure 46, item 4) to hold the deployment bag closed. Insert
a packing paddle (figure 46, item 5) through the connector link tie loops (figure 46, item 6).
6
1
2
5
4
3
Figure 46. Closing Deployment Bag and Stowing Suspension Lines (continued)
3. Lay the deployment bag down. Grasp all suspension lines (figure 47, item 1) and form a loop, which
reaches from the center of the deployment bag to 2 inches beyond the hood of locking stow loop.
4. Insert right stow hook (figure 47, item 2) through loop formed by suspension lines. Ensure that the
stow hook is around all of the suspension lines.
0015 00-31